Dwarf cancels construction of Wall: Creature occupying site
This error occurs all too often when a dwarf is trying to build a wall and chooses to stand in the tile of the wall-to-be-built.Bug:5991 This appears to be fallout from the change to prevent dwarves from walling themselves out of the fortress.
To resolve this problem, try the following (roughly in order of ease):
- Cancel the construction, then reissue the job.
- Place a suspended wall construction order in the tile that they have been approaching the wall from. They will try to avoid standing in this place while building and it can cause them to path differently to the construction site, possibly avoiding the bug. This can also be used to keep dwarves from walling themselves into places, by putting a suspended wall construction order on the side which, if they stood in while building the wall, they would wall themselves in.
- Designate "restricted" traffic areas to force the dwarf to approach the build site from a more favorable direction.
- If the wall is being placed on soil or another natural floor, channel the building site to prevent the dwarf from standing there (walls can be built on open space, as long as there is an adjacent floor tile). Note that this will not work if the only access to the building site is diagonal.
- Create an alternate path to the build site (dig a tunnel, remove a wall, or build a floor).
To avoid this problem, attempt to follow best practices:
- Don't submit building jobs on a tile where a dwarf is standing.
- For constructions in tight quarters, submit any "problematic" tiles first, wait for them to be built, then submit the rest.
- For large constructions in the open, submit all the jobs at a single time by using u or k.
- Don't issue build orders that will intentionally strand the builder--rather than wall themselves out, they will cause this error (which is still better than silently starving to death).
- If you expect problems, preemptively designate restricted traffic areas or channel the build site.
Another way of bypassing this is to build a floor on the tile then remove it and immediately build the wall in its place, the dwarf will be standing to the side of the wall from building the floor.
Explanation
To successfully build a wall, the builder's path to the construction site must pass through an adjacent tile from which construction is allowed. There are several reasons why this might not occur, leading the builder to stand on the building site:
If the builder is already standing on the construction site then no pathing is performed; the builder will simply "choose" the construction site. Canceling and resubmitting the work order when the builder is not standing on the construction site will resolve this problem.
If the builder's chosen path is later rendered impassible (say, by another construction being built), the builder will choose to stand on the construction site instead of selecting another valid adjacent tile. In this case, canceling and reissuing the build order will cause the builder to re-path, solving the problem.
If the shortest path to the build site only crosses unsuitable tiles (most often because of ramps) then the builder will choose to stand on the construction site. In this case reissuing the build order is insufficient; the builder must be encouraged to approach the build site from a different direction (using traffic designations, constructions, locked doors, etc.).
In all cases rendering the building site impassible (by channeling) will force the builder to path through and stand on an acceptable adjacent tile; if no such path exists the build order cannot be submitted.